Paving Schedule Changed
The Hall Company had to make changes to the paving schedule due to unanticipated issues maintaining traffic flow in the community. They paved East Pebble Beach Circle on 3/01/22 instead of West Winged Foot Circle as planned. All milling is complete and paving will continue throughout the week. Please understand that additional changes may be made to the paving schedule as needed. Thank you for your patience and understanding.